Project Duration
Stipulated Date of Commencement
November 15 2018
Stipulated Date of Completion /
Likely Date of Completion August 15 2019
Likely Date of Completion August 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,968,423.00
Awarded for
₹ 13,587,959.00
Project highlights
Roofing work, Tilling work Painting , Repairing of window & doors,plumbing works, electrical works, etc.
Contractors
M/s. Sri Sri Akruthi Projects Pvt. Ltd
Consultants
M/s Bhaskar Wagle & Associates