Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion June 09 2019
Likely Date of Completion June 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,557,570.00
Awarded for
₹ 3,871,916.24
Project highlights
Repairs/Upgradation and Maintenance work – Civil, Plumbing and Electrical works, sanitary work, land development, compound wall, etc.
Contractors
M/s. R.G. Contractors & Engineers
Consultants
M/s Nitin Arolkar