Project Duration
Stipulated Date of Commencement
May 23 2013
Stipulated Date of Completion /
Likely Date of Completion August 22 2013
Likely Date of Completion August 22 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,265,380.00
Awarded for
₹ 7,015,854.00
Project highlights
School Building with 4 classrooms of international size 60 sq. m
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Datta Kare Associates
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Ponda Taluka: Package-C (GPS Kaungal Savai Verem, GPS Pali Savai Verem, GPS Savai Verem & GPS Vagurme Savai Verem)
View Project
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-C
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works in Bicholim Taluka- Package A-(G.P.S. Kahtar Dabdaba, G.P.S. Lamgao, G.P.S. Bagwada Pilgao, G.P.S. Mathwada Pilgao)
View Project