Project Duration
Stipulated Date of Commencement
December 11 2021
Stipulated Date of Completion /
Likely Date of Completion August 10 2022
Likely Date of Completion August 10 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,57,02,662.81
Awarded for
₹ 8,86,24,433.05
Project highlights
Construction of 40m four lane brisge across river Tar at Mapusa
Contractors
M/s. PRN Infratech
Consultants
M/s.Madhav Kamat & Associates