Project Duration
Stipulated Date of Commencement
January 22 2003
Stipulated Date of Completion /
Likely Date of Completion July 21 2003
Likely Date of Completion July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,631,835.00
Awarded for
₹ 29,280,000.00
Project highlights
• Length : 40 m.
• The bridge consists of cast-in-situ continuous R.C.C. T beam superstructure.
• Carriage way 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Uguem and Kalay side.
• Electric poles with fixtures on the bridge and approaches.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates