Project Duration
Stipulated Date of Commencement
January 22 2003
Stipulated Date of Completion /
Likely Date of Completion July 21 2003
Likely Date of Completion July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at
₹ 24,631,835.00
Awarded for
₹ 29,280,000.00
Project highlights
• Length : 40 m.
• The bridge consists of cast-in-situ continuous R.C.C. T beam superstructure.
• Carriage way 7.5 m wide with kerbs, railings and footpaths on both the sides.
• Approaches on Uguem and Kalay side.
• Electric poles with fixtures on the bridge and approaches.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.
View Project
Construction of Bridge for local farmers to cross river stream for cultivation of fields from Chune – Kator to Vanso Field in Village of Cumbarjua.
View Project
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
View Project