Project Duration
Stipulated Date of Commencement
March 26 2016
Stipulated Date of Completion /
Likely Date of Completion October 25 2016
Likely Date of Completion October 25 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,01,07,22.00
Awarded for
₹ 166,366,827.50
Project highlights
Widening of existing road alongwith hotmixing
Contractors
M/s. Ritesh Developers Pvt. Ltd.
Consultants
M/s. TPF Engineering Pvt. Ltd.
(formerly known as M/s. S.N. Bhobe Associates)
See Similar Projects
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable
View Project
Refurbishment of Pedestrian Bridge linking Central Library and creek.
View Project
Demolition Of Existing Bridge And Reconstruction Of Box Culvert On 18th June Road Over St. Inez Creek, Panaji
View Project





