Project Duration
Stipulated Date of Commencement
January 10 2009
Stipulated Date of Completion /
Likely Date of Completion July 09 2010
Likely Date of Completion July 09 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 122,736,085.00
Awarded for
₹ 152,368,897.50
Project highlights
Bridge across river MADEI linking villages Guleli and Padeli.
Contractors
M/s. Aditya Construction Company
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.