Project Duration
Stipulated Date of Commencement
February 10 2007
Stipulated Date of Completion /
Likely Date of Completion November 10 2007
Likely Date of Completion November 10 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,851,870.00
Awarded for
₹ 45,500,000.00
Contractors
M/s. Aditya Construction Company
Consultants
M/s. Keni & D’Souza