Project Duration
Stipulated Date of Commencement January 05 2004
Stipulated Date of Completion /
Likely Date of Completion
July 04 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,750,000.00
Awarded for ₹ 12,880,000.00

Project highlights

• Length : 90 m.
• Carriage way 4.5 m wide with kerbs and railings on both the sides.
• Five spanned with two abutments and four piers all of which are resting on open foundation.

 
Gallery Image
Contractors
M/s. Descon
Gallery Image
Consultants
M/s. Kuvelkar Salkar Associates
 
Similar Projects

See Similar Projects

Similar Project

Hotmixing at Margao Bus Stand.

View Project
Similar Project

Improvement / Widening of road in Saligao – Calangute Constituency.

View Project
Similar Project

Improvement and Widening to four lane road from km.34/200 to km.35/600 at Navelim including construction of pavement at various places.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.