Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion April 21 2014
Likely Date of Completion April 21 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 47,818,331.00
Awarded for
₹ 49,410,097.00
Project highlights
Hot mixing of road
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Madhav Kamat & Associates