Project Duration
Stipulated Date of Commencement February 26 2021
Stipulated Date of Completion /
Likely Date of Completion
August 25 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 35,271,089.34
Awarded for ₹ 33,109,911.26

Project highlights

Provided 50No’s bus bays, 11 nos tempo parking, 44nos 4wheelers parking, 64 nos two wheelers, shed for travellers, drivers room, canteen room, kitchen area, toilet block, high mast and separate 10m wide road for market yard.

 
Gallery Image
Contractors
M/s. Samarth Construction
Gallery Image
Consultants
M/s. Rahul Deshpande & Associates
 
Similar Projects

See Similar Projects

Similar Project

Maintenance of bridges constructed by GSIDC for a period of five years (South Goa) :- Civil works.

View Project
Similar Project

Hot mixing & Improvement of Internal Roads in V. P. St. Jose de Areal in Velim Constituency.

View Project
Similar Project

Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.