Project Duration
Stipulated Date of Commencement June 24 2006
Stipulated Date of Completion /
Likely Date of Completion
April 23 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 111,151,947.00
Awarded for ₹ 141,357,588.70

Project highlights

The length of the road is 26.5 km. The work involves hot mixing of the road, construction of site gutters, retaining walls including pipe culverts cross drainages, road signages & marking, crash barriers.

 
Gallery Image
Contractors
M/s. D. S. Contractors Private Limited
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Construction of bridge across river between Aldona and Calvim.

View Project
Similar Project

Construction of Bus Stand at Shiroda – Phase II : Civil works, internal electrification and road

View Project
Similar Project

Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.