Project Duration
Stipulated Date of Commencement
September 19 2022
Actual Date of Completion
May 15 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 55,590,132.35
Awarded for
₹ 53,712,065.00
Project highlights
Hostel rooms with attached toilets, Guest room, Dinning, Library, open courtyard, indoor room, recreationla facilities, Laundary room, parking facilities etc…
Contractors
M/s A.R. Construction
Consultants
M/s Amit Sukthankar
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Pernem Taluka: Package-IV (GPS Naikwada Palye, GPS Bhandarwada Palye, GPS Deulwada Mandre, GPS Naikwada Mandre, GPS Deulwada Morjim)
View Details
Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).
View Details
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package J (G.P.S Valshi, G.P.S. Ussap, G.P.S. Kharpal and G.P.S Dhangarwada)
View Details