Project Duration
Stipulated Date of Commencement February 23 2019
Stipulated Date of Completion /
Likely Date of Completion
September 22 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,935,425.00
Awarded for ₹ 12,205,472.53

Project highlights

Repairs/Upgradation of G.P.S Valshi, G.P.S. Ussap, G.P.S. Kharpal and G.P.S Dhangarwada

 
Gallery Image
Contractors
M/s. Sirajuddin Beig
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Construction of Government Primary School at Tonca, Camrabhat in Tiswadi taluka.

View Project
Similar Project

To Prepare a Master Plan for Mormugao Constituency SH: Swimming pool

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.