Project Duration
Stipulated Date of Commencement October 04 2021
Actual Date of Completion March 31 2024
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,598,613.23
Awarded for ₹ 28,794,751.15

Project highlights

At present Cumbarjua farmers having fields in Jua Village have to cross water tributary from Cumbarjua to Jua Village to access their fields. Proposed bridge will fulfill the long-standing demand of the farmers to access their fields. The bridge will cater to foot traffic and tractor movement.
Construction of Bridge of total length of 50 mtrs. , Carriage way of 3 mtrs, to provide single lane for tractor traffic.

 
Gallery Image
Contractors
M/s. KVJ Builders and Developers
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and Construction of Bridge at Ambeshi – Ganjem over Mhadei river.

View Details
Similar Project

Civil & Electrical works

View Details
Similar Project

Construction of Bus Stand at Shiroda – Phase I : Land Development

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.