Project Duration
Stipulated Date of Commencement December 11 2014
Actual Date of Completion August 31 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,055,616.00
Awarded for ₹ 55,882,025.78

Project highlights

Development of service road and site development at Mont Boa Vista which includes surface excavation ,laying of 40mm thick BM,25mm thick Asphalt Concrete , Providing and laying of BMC ,laterite masonary etc.

 
Gallery Image
Contractors
M/s.Jagdish Pai
Gallery Image
Consultants
M/s.Manguesh Prabhugaonkar
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Construction of Market complex and multipurpose hall at V.P Dongurli- Thane.

View Details
Similar Project

Interior Work

View Details
Similar Project

Supply,Installation,Testing and Commissioning of streetlight poles and fixtures along with allied electrical works for the stretch from NIO Circle to Miramar circle, NIO circle to Rajbhavan, NIO circle to Dona Paula Jetty & NIO circle to Odxel Junction

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.