Project Duration
Stipulated Date of Commencement February 22 2008
Actual Date of Completion August 01 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,780,533.00
Awarded for ₹ 9,700,990.00
Final Cost of Project ₹ 7,681,086.00

Project highlights

Land filling and construction of retaining wall

 
Contractors
M/s. Rohit Equipments
Consultants
M/s. Vijaykumar Sawant Associates
 