Project Duration
Stipulated Date of Commencement
March 17 2011
Actual Date of Completion
January 31 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,45,08,439.00
Awarded for
₹ 4,59,67,465.95
Contractors
M/s. Acron Developers Pvt. Ltd.
Consultants
M/s. Gurudutt Sanzgiri