Project Duration
Stipulated Date of Commencement November 06 2022
Actual Date of Completion December 31 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,138,926.09
Awarded for ₹ 25,393,644.83

Project highlights

The centralised substation will cater to all the building blocks in the campus with proper distribution of power using switch gears.

 
Gallery Image
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. FP Project Management
 
Similar Projects

See Similar Projects

Similar Project

Upgradation and Extension of Existing Cottage Hospital at Chicalim, Goa. S.H. – Supply, Installation, Testing & Commissioning of CCTV system”.

View Details
Similar Project

Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa SH: Maintenance/ Renovation Work of Sub District Hospital at Ponda, Goa – SITC of Split AC Units

View Details
Similar Project

Construction of building with compound wall for 30 bedded hospital at Bicholim – Civil, Plumbing & Electrical works.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.