Project Duration
Stipulated Date of Commencement October 31 2009
Stipulated Date of Completion /
Likely Date of Completion
December 31 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 49,990,185.00
Awarded for ₹ 51,999,999.00

Project highlights

Total built up area – 3244 m2. Facilites include Wards for male and female with toilets and nurse station, pharmacy, casualty, consulting rooms, ICU, OT, Paid wards, Office, canteen, doctors rest rooms. Hospital is provided with lift, ramp, medical gases line, Air conditioning, fire fighting and fire alarm system, medical and non medical furniture, solar water heating system and generator backup

 
Gallery Image
Contractors
M/s. Acron Developers
Gallery Image
Consultants
Datta Kare Associates
 

Sub Works

This project involved 9 sub works. The details of the same available below

1

Lift work.

100% completed
 
Project Duration
Stipulated Date of Commencement February 17 2011
Stipulated Date of Completion /
Likely Date of Completion
July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,087,400.00
Awarded for ₹ 2,220,000.00
 
Contractors
Contractors
M/s. Eagle Construction Co.
Consultants
Consultants
Datta Kare Associates
2

Air conditioning work

100% completed
 
Project Duration
Stipulated Date of Commencement April 02 2011
Stipulated Date of Completion /
Likely Date of Completion
August 01 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 33,86,391.00
Awarded for ₹ 35,09,999.00
 
Contractors
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Consultants
Datta Kare Associates
3

Steel Operation Theatre.

100% completed
 
Project Duration
Stipulated Date of Commencement April 02 2011
Stipulated Date of Completion /
Likely Date of Completion
September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 81,57,300.00
Awarded for ₹ 66,66,600.00
 
Contractors
Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.
Consultants
Consultants
Datta Kare Associates
4

Medical gases & vacuum system works

100% completed
 
Project Duration
Stipulated Date of Commencement April 02 2011
Stipulated Date of Completion /
Likely Date of Completion
September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 28,20,149.00
Awarded for ₹ 27,09,910.00
 
Contractors
Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.
Consultants
Consultants
Datta Kare Associates
5

Solar water heating system.

100% completed
 
Project Duration
Stipulated Date of Commencement July 07 2011
Stipulated Date of Completion /
Likely Date of Completion
August 05 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 402,850.00
Awarded for ₹ 407,375.00

Project highlights

Solar water heating system for bathrooms

 
Contractors
Contractors
M/s. B. R. Enterprises
Consultants
Consultants
Datta Kare Associates
6

External electrical work

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2011
Stipulated Date of Completion /
Likely Date of Completion
September 04 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,320,372.00
Awarded for ₹ 2,484,939.25
 
Contractors
Contractors
M/s. Eagle Construction Co.
Consultants
Consultants
Datta Kare Associates
7

Fire fighting work.

100% completed
 
Project Duration
Stipulated Date of Commencement May 05 2011
Stipulated Date of Completion /
Likely Date of Completion
August 04 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,600,123.00
Awarded for ₹ 1,838,534.00
 
Contractors
Contractors
M/s. Max Alert Systems Pvt. Ltd.
Consultants
Consultants
Datta Kare Associates
8

Furniture works.

100% completed
 
Project Duration
Stipulated Date of Commencement June 16 2012
Stipulated Date of Completion /
Likely Date of Completion
September 13 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 16,183,092.00
Awarded for ₹ 14,742,636.40

Project highlights

Furniture work

 
Contractors
Contractors
M/s. Floor-Space
Consultants
Consultants
Datta Kare Associates
9

UPS works.

100% completed
 
Project Duration
Stipulated Date of Commencement August 31 2013
Stipulated Date of Completion /
Likely Date of Completion
September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,044,105.30
Awarded for ₹ 1,095,570.00
 
Contractors
Contractors
M/s. Paulbern Enterprises
Consultants
Consultants
Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa SH: Medical Furniture works

View Project
Similar Project

Micro -Vascular Instruments

View Project
Similar Project

Civil works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.