Project Duration
Stipulated Date of Commencement
October 31 2009
Stipulated Date of Completion /
Likely Date of Completion December 31 2010
Likely Date of Completion December 31 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,990,185.00
Awarded for
₹ 51,999,999.00
Project highlights
Total built up area – 3244 m2. Facilites include Wards for male and female with toilets and nurse station, pharmacy, casualty, consulting rooms, ICU, OT, Paid wards, Office, canteen, doctors rest rooms. Hospital is provided with lift, ramp, medical gases line, Air conditioning, fire fighting and fire alarm system, medical and non medical furniture, solar water heating system and generator backup

Contractors
M/s. Acron Developers

Consultants
Datta Kare Associates
Sub Works
This project involved 9 sub works. The details of the same available below
1
Lift work.
100% completed
Project Duration
Stipulated Date of Commencement
February 17 2011
Stipulated Date of Completion /
Likely Date of Completion July 16 2011
Likely Date of Completion July 16 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,087,400.00
Awarded for
₹ 2,220,000.00

Contractors
M/s. Eagle Construction Co.

Consultants
Datta Kare Associates
2
Air conditioning work
100% completed
Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion August 01 2011
Likely Date of Completion August 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 33,86,391.00
Awarded for
₹ 35,09,999.00

Contractors
M/s. Aprant Motors Pvt. Ltd.

Consultants
Datta Kare Associates
3
Steel Operation Theatre.
100% completed
Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion September 01 2011
Likely Date of Completion September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 81,57,300.00
Awarded for
₹ 66,66,600.00

Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.

Consultants
Datta Kare Associates
4
Medical gases & vacuum system works
100% completed
Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion September 01 2011
Likely Date of Completion September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,20,149.00
Awarded for
₹ 27,09,910.00

Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.

Consultants
Datta Kare Associates
5
Solar water heating system.
100% completed
Project Duration
Stipulated Date of Commencement
July 07 2011
Stipulated Date of Completion /
Likely Date of Completion August 05 2011
Likely Date of Completion August 05 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 402,850.00
Awarded for
₹ 407,375.00
Project highlights
Solar water heating system for bathrooms

Contractors
M/s. B. R. Enterprises

Consultants
Datta Kare Associates
6
External electrical work
100% completed
Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion September 04 2011
Likely Date of Completion September 04 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,320,372.00
Awarded for
₹ 2,484,939.25

Contractors
M/s. Eagle Construction Co.

Consultants
Datta Kare Associates
7
Fire fighting work.
100% completed
Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion August 04 2011
Likely Date of Completion August 04 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,600,123.00
Awarded for
₹ 1,838,534.00

Contractors
M/s. Max Alert Systems Pvt. Ltd.

Consultants
Datta Kare Associates
8
Furniture works.
100% completed
Project Duration
Stipulated Date of Commencement
June 16 2012
Stipulated Date of Completion /
Likely Date of Completion September 13 2012
Likely Date of Completion September 13 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,183,092.00
Awarded for
₹ 14,742,636.40
Project highlights
Furniture work

Contractors
M/s. Floor-Space

Consultants
Datta Kare Associates
9
UPS works.
100% completed
Project Duration
Stipulated Date of Commencement
August 31 2013
Stipulated Date of Completion /
Likely Date of Completion September 30 2013
Likely Date of Completion September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,044,105.30
Awarded for
₹ 1,095,570.00

Contractors
M/s. Paulbern Enterprises

Consultants
Datta Kare Associates