Project Duration
Stipulated Date of Commencement
December 12 2011
Actual Date of Completion
May 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,528,636.00
Awarded for
₹ 5,976,204.30
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of Mortuary Cabinet.
100% Completed
Project Duration
Stipulated Date of Commencement
December 01 2011
Actual Date of Completion
May 29 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,058,320.00
Awarded for
₹ 2,406,250.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Datta Kare Associates