Project Duration
Stipulated Date of Commencement
January 21 2013
Stipulated Date of Completion /
Likely Date of Completion May 20 2013
Likely Date of Completion May 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 411,664.00
Awarded for
₹ 492,000.00
Project highlights
Motruary Cabinet Works
Contractors
M/s. Megastar Engg., Pune
Consultants
M/s Effective Architectural Services