Project Duration
Stipulated Date of Commencement
February 22 2014
Actual Date of Completion
May 26 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 89,455,485.00
Awarded for
₹ 105,345,058.70
Project highlights
Construction of Government College of Commerce & Economics, college building for Directorate of Higher Education.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. KICONS Limited
Sub Works
This project involved 2 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of CCTV & PA System
100% Completed
Project Duration
Stipulated Date of Commencement
October 31 2016
Actual Date of Completion
November 30 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,904,203.00
Awarded for
₹ 1,649,951.00
Project highlights
CCTV & PA System
Contractors
M/s. Psytech Infosolutions Pvt. Ltd.
Consultants
M/s. KICONS Limited
2
Interior Furniture Works
100% Completed
Project Duration
Stipulated Date of Commencement
April 10 2015
Actual Date of Completion
March 31 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,184,374.00
Awarded for
₹ 16,708,003.14
Project highlights
Interior & Furniture works
Contractors
M/s. Shalaka Infra Tech (I) Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract
View Details
Repairs/Upgradation and maintenance of Government High School at Headland Sada, Vasco, Goa.
View Details
Interior Furniture Works
View Details