Project Duration
Stipulated Date of Commencement July 26 2016
Stipulated Date of Completion /
Likely Date of Completion
September 08 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 999,534.00
Awarded for ₹ 1,044,450.00

Project highlights

The scope of work includes supply, installation, testing & commissioning of :
a) 160kVA,11/.415kV Distribution transformer
b) 11kV Load Break Switch
c) HT Metering cubicle and other allied electrical works.

 
Gallery Image
Contractors
M/s. Aditya Electromech Services
Gallery Image
Consultants
M/s. Archivista Engineering Projects. Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of GHS at Davorlim, Salcete, Goa

View Project
Similar Project

Supply & Installation of Furniture for Government Schools and Colleges in the State of Goa

View Project
Similar Project

Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.