Project Duration
Stipulated Date of Commencement July 19 2018
Actual Date of Completion February 15 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 66,81,190.25
Awarded for ₹ 7,087,775.45

Project highlights

Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.

 
Contractors
M/s ASK Developers
Consultants
M/s. Datta Kare Associates
 