Project Duration
Stipulated Date of Commencement
July 16 2015
Actual Date of Completion
March 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,607,355.05
Awarded for
₹ 6,429,577.99
Contractors
M/s. Kamat Engineering Services
Consultants
Creative Abode
See Similar Projects
Construction of Government Primary School at Tonca, Camrabhat in Tiswadi taluka.