Project Duration
Stipulated Date of Commencement
December 24 2019
Actual Date of Completion
April 20 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 77,957,826.00
Awarded for
₹ 74,565,448.00
Project highlights
The scope of work involved construction of new bypass road from Ambeudak, Sanvordem to Devnamol in V. P. Kalay and Savordem. The total length of the road is 2.14 km, which comprises of construction of retaining wall, culverts, storm water drain, hot-mixing, etc.
Contractors
M/s. Ritesh Developers
Consultants
M/s. Vijaykumar Sawant, And Associates