Project Duration
Stipulated Date of Commencement
December 23 2013
Actual Date of Completion
March 26 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,897,049.00
Awarded for
₹ 41,694,835.00
Project highlights
• Consists of laying of 33 KV & 11 KV underground cables.
• Supply, installation, testing & commissioning of LED street light poles.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Kashec Engineers Pvt. Ltd.