Project Duration
Stipulated Date of Commencement
January 11 2015
Actual Date of Completion
June 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 51,322,507.76
Awarded for
₹ 58,840,435.00
Project highlights
Conversion of electrical overhead lines to underground cables.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s Nitin Arolkar