Project Duration
Stipulated Date of Commencement
November 21 2013
Actual Date of Completion
November 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,455,439.00
Awarded for
₹ 17,090,650.00
Project highlights
Widening & hotmixing of roads
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Widening of road in Calangute – Baga – Electrical works..
100% Completed
Project Duration
Stipulated Date of Commencement
February 11 2014
Actual Date of Completion
June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 860,362.00
Awarded for
₹ 885,228.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.
Contractors
M/s. Aditya Electromech Services
Consultants
In-house
(GSIDC)
See Similar Projects
Construction of bridge between Tharmas to Ozari Sangaowada in Dhargal Constituency.
View Details
Demolition of old Existing jetty and Reconstruction of New Fisheries Jetty at Panaji, Goa
View Details
Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14
View Details