Project Duration
Stipulated Date of Commencement
November 21 2013
Actual Date of Completion
November 30 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,455,439.00
Awarded for
₹ 17,090,650.00
Project highlights
Widening & hotmixing of roads
Contractors
M/s.Assmas Constructions Pvt. LTd
Consultants
M/s.Madhav Kamat & Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Widening of road in Calangute – Baga – Electrical works..
100% Completed
Project Duration
Stipulated Date of Commencement
February 11 2014
Actual Date of Completion
June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 860,362.00
Awarded for
₹ 885,228.00
Project highlights
The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.
Contractors
M/s. Aditya Electromech Services
Consultants
In-house
(GSIDC)
See Similar Projects
Design and Construction of Bridge at Ambeshi – Ganjem over Mhadei river.
View Details
Construction of Bus Stand and Shopping Complex at Assonora
View Details
Construction of Road Bridge at Sanvorcotto on MDR Cuncolim – Quepem Road in Cuncolim Municipal Area.
View Details