Project Duration
Stipulated Date of Commencement
June 20 2008
Actual Date of Completion
September 30 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 48,800,263.00
Awarded for
₹ 62,155,219.80
Contractors
M/s. Madanant Construction (Goa) Pvt. Ltd. (for both Phase I and Phase II separately)
Consultants
M/s. Mahimtura Consultants Pvt. Ltd. (for both Phase I and Phase II separately)