Project Duration
Stipulated Date of Commencement
January 15 2019
Actual Date of Completion
August 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,560,493.00
Awarded for
₹ 1,962,000.00
Final Cost of Project
₹ 1,913,685.00
Project highlights
100 ft Flag Mast System along with 20ftX30ft Indian National Flag
Contractors
M/s. Fluid and Power Automations LLP
Consultants
In house (GSIDC)