Project Duration
Stipulated Date of Commencement
February 16 2007
Actual Date of Completion
October 22 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 91,848,583.00
Awarded for
₹ 132,821,014.00
Project highlights
1) Improvement and upgradation of road network at Piligao in Bicholim taluka. 2) Improvement and upgradation of road network of Curti and Ponda town. 3) Improvement and upgradation of existing road from Chodan Ferry to Thikazem bridge and from State Bank of India, Chodan to Pomburpa ferry.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Technogem Consultants Pvt. Ltd.