Project Duration
Stipulated Date of Commencement
April 23 2016
Stipulated Date of Completion /
Likely Date of Completion October 28 2017
Likely Date of Completion October 28 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 236,470,437.00
Awarded for
₹ 242,441,097.11
Project highlights
Cfonstruction of 2 Lane Bridge with approaches.