Project Duration
Stipulated Date of Commencement
June 24 2006
Actual Date of Completion
December 05 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 111,151,947.00
Awarded for
₹ 141,357,588.70
Project highlights
The length of the road is 26.5 km. The work involves hot mixing of the road, construction of site gutters, retaining walls including pipe culverts cross drainages, road signages & marking, crash barriers.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD