Project Duration
Stipulated Date of Commencement April 07 2006
Actual Date of Completion May 10 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 44,419,884.00
Awarded for ₹ 54,735,320.00

Project highlights

Hot mixing (laying of bituminous macadam and asphaltic concrete), lane marking, providing gutters and cross drainages wherever required. The approximate length of the road is around 14.6 kms.

 
Gallery Image
Contractors
M/s. Madanant Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Keni & D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona.

View Details
Similar Project

Design and Construction of Grade Separator at Dabolim Airport.

View Details
Similar Project

Construction of Pedestrian pathway on existing approach to road over bridge at Rawanfond Margao Goa

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.