Project Duration
Stipulated Date of Commencement
October 04 2021
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
70%
Completed
Cost (₹)
Estimated at
₹ 27,598,613.23
Awarded for
₹ 28,794,751.15
Project highlights
At present Cumbarjua farmers having fields in Jua Village have to cross water tributary from Cumbarjua to Jua Village to access their fields. Proposed bridge will fulfill the long-standing demand of the farmers to access their fields. The bridge will cater to foot traffic and tractor movement.
Construction of Bridge of total length of 50 mtrs. , Carriage way of 3 mtrs, to provide single lane for tractor traffic.
Contractors
M/s. KVJ Builders and Developers
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Design and construction of bridge connecting Keri to Tiracol
View ProjectConstruction of 6-lane Road Over Bridge (ROB) including approaches at Rawanfond, Margao
View ProjectConstruction of four lane bridge at Sanguem Town.
View Project