Project Duration
Stipulated Date of Commencement
May 26 2006
Actual Date of Completion
February 07 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,014,669.00
Awarded for
₹ 32,205,615.00
Project highlights
Main work involved widening of existing road including hot mixing, improvement of existing drainage system, signages, etc. The approximate length of the road is around 8.2 kms
Contractors
M/s. E. O. Thomas & Co.
Consultants
M/s. Madhav Kamat & Associates