Project Duration
Stipulated Date of Commencement June 15 2018
Actual Date of Completion June 18 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,204.00
Awarded for ₹ 45,312.00

Project highlights

The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Improvement and Upgradation of road network from MDLB Hospital to Baina Sea Shore, Shafi Masjid to Baina Recreational Club, Bharat lines to Headland Sada Junction in Mormugao Constituency.

View Details
Similar Project

Construction of Pirna Ozrim bridge including approaches.

View Details
Similar Project

Demolition of Old existing jetty and Reconstruction of New Captain of Ports jetty at Old Goa.

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.