Project Duration
Stipulated Date of Commencement January 08 2018
Stipulated Date of Completion /
Likely Date of Completion
January 22 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,181,939.00
Awarded for ₹ 3,492,794.00

Project highlights

Providing Streetlight Poles from Colva circle to Ravindra bhavan Circle.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
M/s. Ankit Prabhudessai
 
Similar Projects

See Similar Projects

Similar Project

Improvement / Hot mixing of roads in Arpora – Baga.

View Project
Similar Project

Demolition of old Existing jetty and Reconstruction of New Fisheries Jetty at Panaji, Goa

View Project
Similar Project

Comprehensive electrical underground cabling work at Bambolim.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.