Project Duration
Stipulated Date of Commencement
January 08 2018
Stipulated Date of Completion /
Likely Date of Completion January 22 2018
Likely Date of Completion January 22 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,181,939.00
Awarded for
₹ 3,492,794.00
Project highlights
Providing Streetlight Poles from Colva circle to Ravindra bhavan Circle.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Ankit Prabhudessai
See Similar Projects
Widening of roads and relocation of structures in Fatorda Constituency- Phase II
View Project
Construction of Concrete Pavement Road and other development work from Miramar Circle to NIO Circle and Raj Bhavan
View Project
Construction of Bus Stand at Honda.
View Project