Project Duration
Stipulated Date of Commencement October 23 2012
Actual Date of Completion June 30 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,383,028.75
Awarded for ₹ 22,999,093.20

Project highlights

The RCC Simply supported Bridge is (Approx.) 35m in length comprising of 02 spans (approx. 17mts) supported by a central pier and on two abutment walls on both banks of the rivulet. •
The total length of approach roads is approx 400mts.

 
Gallery Image
Contractors
M/s. Indiana Build Infrastructure Pvt. Ltd.
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates (PMC)
 
Similar Projects

See Similar Projects

Similar Project

Construction of bridge at Paikul, Sattari-Goa

View Details
Similar Project

Improvement / Widening of road in Saligao – Calangute Constituency.

View Details
Similar Project

Construction of Bridge across Rua de Ourem Creek, Panaji

View Details
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.