Project Duration
Stipulated Date of Commencement
March 15 2008
Actual Date of Completion
January 08 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 40,071,151.00
Awarded for
₹ 63,000,000.00
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd.