Project Duration
Stipulated Date of Commencement
November 11 2012
Actual Date of Completion
October 12 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 613,673,260.91
Awarded for
₹ 548,475,269.00
Project highlights
The bridge project is of significant importance to the villagers of Aldona and Calvim as the people were very much dependent on the ferry boat service plying between the two villages prior to the construction of the bridge. Construction of this bridge has mitigated the difficulties of the people in crossing the river, especially during the monsoon season. It is also proposed to promote Calvim village as a tourist spot. Thus, the bridge would help in providing easy access to the village
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
See Similar Projects
Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona.
View Details
Construction of bridge at Paikul, Sattari-Goa
View Details
Construction of single lane bridge in village Dongrim, Village Panchayat Azzosim Mandur – Approach road work
View Details