Project Duration
Stipulated Date of Commencement
March 15 2004
Actual Date of Completion
December 31 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,231,864.00
Awarded for
₹ 27,500,000.00
Contractors
M/s. Engineers Combine
Consultants
M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant