Project Duration
Stipulated Date of Commencement
December 12 2016
Stipulated Date of Completion /
Likely Date of Completion January 25 2017
Likely Date of Completion January 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,039,447.00
Awarded for
₹ 12,710,482.00
Project highlights
The scope of work includes:
a) Supply, installation, testing & commissioning of 86 Watts, LED outdoor street lights along with 9 mtrs height hot dip galvanized PU painted conical poles with single arm brackets-109 nos.
b) Supply of 40 Watts, LED outdoor street lights along with 6 mtrs height hot dip galvanized PU painted conical poles with single arm brackets-13 nos.
Contractors
M/s. James Electrical
Consultants
In-house
(GSIDC)