Project Duration
Stipulated Date of Commencement
February 26 2021
Actual Date of Completion
March 31 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,271,089.34
Awarded for
₹ 33,109,911.26
Project highlights
Provided 50No’s bus bays, 11 nos tempo parking, 44nos 4wheelers parking, 64 nos two wheelers, shed for travellers, drivers room, canteen room, kitchen area, toilet block, high mast and separate 10m wide road for market yard.
Contractors
M/s. Samarth Construction
Consultants
M/s. Rahul Deshpande & Associates