Project Duration
Stipulated Date of Commencement October 04 2021
Stipulated Date of Completion /
Likely Date of Completion
July 03 2022
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,598,613.23
Awarded for ₹ 28,794,751.15

Project highlights

At present Cumbarjua farmers having fields in Jua Village have to cross water tributary from Cumbarjua to Jua Village to access their fields. Proposed bridge will fulfill the long-standing demand of the farmers to access their fields. The bridge will cater to foot traffic and tractor movement.
Construction of Bridge of total length of 50 mtrs. , Carriage way of 3 mtrs, to provide single lane for tractor traffic.

 
Gallery Image
Contractors
M/s. KVJ Builders and Developers
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Design and Construction of Grade Separator at Dabolim Airport.

View Project
Similar Project

Comprehensive electrical underground cabling work at Bambolim.

View Project
Similar Project

Construction of Pedestrian Arch Bridge connecting Mandovi River Promenade and DB Road, over St. Inez Creek near ESG Building at Panaji

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.