Project Duration
Stipulated Date of Commencement
December 28 2014
Stipulated Date of Completion /
Likely Date of Completion December 03 2014
Likely Date of Completion December 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,309,655.00
Awarded for
₹ 2,956,518.00
Contractors
M/s. Psytech Infosolutions (India) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services
See Similar Projects
Additional civil work.