Project Duration
Stipulated Date of Commencement
October 06 2016
Stipulated Date of Completion /
Likely Date of Completion June 05 2017
Likely Date of Completion June 05 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,232,668.00
Awarded for
₹ 25,285,337.00
Project highlights
repair upgradation of the Azad Maidan sqaure with painting, pavers, lanscaping & construction of new toilet block
Contractors
M/s. Premier Builders (Goa) Pvt. Ltd.
Consultants
M/s. LKS India Pvt Ltd.