Project Duration
Stipulated Date of Commencement
July 15 2019
Stipulated Date of Completion /
Likely Date of Completion November 14 2019
Likely Date of Completion November 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 221,496,176.00
Awarded for
₹ 204,287,929.54
Project highlights
False ceiling, interior, furniture signage, security installation and other miscellaneous works. Interior works for the new High Court building includes false ceilings, furniture, signages etc.
Contractors
M/s. Siddhi Construction,
Consultants
See Similar Projects
Supply, installation, testing and commissioning of 315 KVA transformer.